News

  • Kiata Wind Farm completes erection of all turbines - Published on: 9 Oct 2017 - 12:13pm

    October 9, 2017: The ninth and final 3.45MW turbine was successful completed over the week end with the rotor lift.  The project will now undergo approximately six weeks of testing and commissioning before being placed in full production in early December.

     

  • Kiata Wind Farm Begins Construction - Published on: 22 Mar 2017 - 12:12pm

    Kiata, Victoria, 21 March 2017: Victoria’s Renewable Energy Advocate Mr Simon Corbell today turned the first sod for construction of Kiata Wind Farm, at an on-site ceremony attended by landowners, investors and members of the local community.